QEW/Glendale Interchange Paving Starting Next Week

Approximate work area on QEW at QEW/Glendale Interchange. Photo Credit: Morrison Hershfield

Milling and paving work taking place on the QEW from the Garden City Skyway to Highway 405

A word of warning if you take the QEW. 

Milling and paving operations are expected to start on Monday from the Garden City Skyway to Highway 405.

Engineering company Morrison Hershfield says operations are expected to take four to six weeks. 

The following impacts can be expected during operations: 

  • Alternating two of three lanes will be closed during nightly closures in both directions on the QEW.
  • On and off ramps will be closed periodically as required when operations are in and around the QEW/Glendale interchange.
  • Highway 405 Toronto Bound will be closed at Stanley Avenue periodically as required when operations are in and around the merging lanes of Highway 405 to QEW Toronto Bound. 
  • Highway 405 Niagara Bound will be closed at the QEW periodically as required when operations are in and around the merging lanes of the QEW to Highway 405 Niagara Bound. 

The company says additional notices will be distributed in advance of Highway 405 Closures.